Skip to content

Feature - Material Work Order Inquiry Material Used

Release Date: 1/7/19

When entering a production transaction for a material work order, the user has the ability to add other material used at the time of production. This may be required if a component is not available at production time and a substitution was made. This feature allow the user to view the material that was used during production in Material Work Order Inquiry.

After entering the production work order number, the Component Data screen is shown by default.


 
A new F7=Mtrl Used option is available if the work order is partially complete or complete. When you press the F7 key, the application will show the actual material used instead of the standard component data.



From this screen the user can press the F7 key to return to the component data screen.

Programs Modified: BMORDINQ
CLS