BMWOPROD Bill of Material Work Order Production

Work Order Production

 

How to Access:

Main Menu è Distribution è Bill of Material Processor è Maintenance è Work Order Production

 

 

Work Order Production, Typing Mode

 

 

This is the Time Clock Interface for Work Order Reporting.  It is for workers who report when production starts and when production ends.  When production ends, the system will ask for the production result of how many pieces are completed.  It will collect labor time from these workers and add it to work orders as direct labor.  There are only 3 stages in this screen:

  • In the first stage, the operator needs to enter the Operator ID and password, which can be entered by scanning a badge.
  • In the second stage, the operator needs to report the function, like progress on a work order or a special operation like a break.
  • In the third stage, the operator needs to report how many pieces were finished for the production if working on a work order.
  • Based on the BOMP Global Setup, control will return to the first stage or second stage.

 

The operator always needs to enter the activity.  The system will determine if this ends an operation and prompt for additional information if necessary.  At the end of the day, the operator needs to “start” a special operation, End of Day, to log off.

First Stage – Sign in

 

 

Work Order Production, Scanning Mode

 

 

The operator must first enter an Operator ID and password.  To manually type the data, you must enter the Operator ID, press Enter, type the password and press Enter again.  On the other hand, you can scan the barcode on a badge.  Press the F1 Key to toggle between scanning mode and manual mode.  The barcode scanning mode will prompt for a much longer string to allow for both fields.  After successfully authenticated, the system will display on the top 3 lines information about the operator and what this operator is currently doing.

 

The operator can currently log off the system, work on a production, work in a work center, or perform a special operation like a break.  The system will display different details for different activities.

 

On the right side of the third line is a two decimal number.  This is the elapsed time of the current activity in hours.

 

The system will prompt for the order number after the first stage.

Second Stage – Next Activity

 

 

Work Order Production, After First Stage

 

 

In the second stage, the operator can report what to do next.  This can be to start a new production, resume a suspended production, report for a current production, start a break, go to a meeting or log off from the system at the end of the day.  Each activity is defined as an operation in WO+ and each operation has its own number.  These are the numbers that are entered in the second stage.  They can be scanned if a barcode is provided for these numbers.

 

There are two operation types for different activities, Order Operation and Special Operation.  Order Operations are those defined in the routing of work orders and are used for production activities.  The work order number and order operations must be entered. Special Operations are for activities other than production related.  Special Operations can represent a break, a meal break, a log off or other purpose.  So to report production related activity, use the Order Operation and the operations listed on the Traveler.  Otherwise, use a Special Operation.  The figure above and the figure below show the screens after entering an Order Operation or Special Operation, respectively.

 

 

Work Order Production, Start a Work Order

 

 

 


 

Work Order Production, Start a Break

 

 

 

Field Description in Stage 2

 

Name

Type and Description

Order Number

6 numeric digits.

The order number of an ongoing production.  If a special operation will be entered, this field can be blank.

Function Keys

F1     - Start a Batch Production.  A Batch Production allows you to work on multiple work orders at the same time.  Labor and Machine time will be distributed to each work order based on reported quantity.

F3     - Advanced Options.  Options include inquiry of the current status (operator time clock or production status) and changing the interface behavior.

·      Operation Time Clock

·      Current Production Detail

·      Current Production Activity Inquiry

·      Production Inquiry for the Current Work Order

·      Production Inquiry for the Current Operation

·      Change ID Prompt Setting

F4     - Exception Handling.  Exception handling options to change the activity time or change the current activity content.

·      Reassign Current Time Clock Activity

·      Change End Time

F7     - Enter a Production Number.  If the Production Number is known, you can enter it instead of entering the order number and operation number.  Normally, the system will automatically determine the proper production number after the order number and operation number are entered.

Defaults to the current work order number.

Operation Number

4 numeric digits.

The operation number of an ongoing activity.  If the order number is blank, this field can only be a special operation.  Otherwise, it can be both an order operation and special operation.

Function Key

F7     - Search for an order operation, if the order number is not blank.  Search for a special operation, if the order number is blank.

F8     - Search for a special operation, if the order number is not blank.

The system determines the next activity based on the operation number.

·      If the operation number entered is the same as the current activity, this means the operator wants to end the current activity and the next activity has not been assigned.  The system will change the operator’s current activity to “Idle”.

·      If the operation number is for a special operation (from 9000 thru 9999), the system will determine the next activity based on the operation type.

o        For a break, productive and non-productive operation types, the system will change the operator’s current activity status.

o        For a meal break and End Of Day operation types, the system will log the operator off and the activity status.

o        For monitor operation types, like W and D, the system will change the operator’s activity to a work center or department shared labor.

·      If the operation number is an order operation, from 1 thru 8999, the system will try to determine the production number.

o        If the productions for this operation are not yet started, all completed or all worked on by another operator, the system will assume the operator wants to start a new production for this operation.

o        If any production is suspend or active without an operator and the production was previously worked on by the operator, the system will assume the operator wants to resume, continue or report for that production.

o        If the system is unable to determine the production number, a list of productions will be presented for the operator to choose from.

If the operator is going to start a production for an outside process, the system will prompt for PO related information, like vendor number and PO number.  You can enter this information now or when reporting.

Plan Quantity

Standard quantity format.

Enter the planning quantity for a new production.

Function Key

F4     - Change Operation.  If this operation has not been started, you can change the value for this operation.

Confirmation

1 alpha-numeric character.

After entering all information about the next activity, the system will prompt for confirmation.

This confirmation question may vary based on the next activity.  For example, if you want to start a suspended production, the system will prompt “S = Start This Operation, R = Report This Operation”.  The latter option will allow you to directly report for the production without scanning the same operation number again.

 


Third Stage – Current Production Reporting

 


 

Work Order Production, Third Stage

 

 

If the operator’s activity is for a special operation, like a break or meeting, the system will change the status to the next activity.  The operator will not need to report for the current activity, except for a required comment.  Otherwise, the operator will be required to report for the current production before starting the next activity.  This will bring you to the third stage, current production reporting.

 

In most cases, the only requirement is to enter the quantity of completed pieces.  However, WO+ provides several functions for different situations.

  • Usually, only the completed pieces and the quantity need to be reported.  However, the quantity entered should not be zero.  If this operation is a material issued point, the system will show the list of issued material to confirm. If this operation is the last operation and the product is a serialized item, the system will prompt for a serial number.
  • If the operator wants to stop working on the production, but the production is not completed, a zero can be entered in the Qty Completed field.  This usually means production is suspended, but in some cases, like with a CNC Machine, the production can be continued without an operator.  The literal right of the “End Date/Time” will indicate if the production will be reported, suspended or continued without an operator.  You can report if a CNC machine will continue running or not by pressing F3 for Advance Option and selecting the “Machine On/Off” to change the status of the machine.  If the machine is off, production will be suspended.  The default value is defined in each work center file through the “(Machine) End By Def If Labor End” field.
  • If some pieces are scrapped during the production, the operator would need to report the quantity scrapped.  There are two ways to report this.
    • If BOMP Global Setup field 52, Warning If Plan & Report Qty Are Different, is set to “Y”, the operator will be prompted for the quantity scrapped.  For example, the prompt for reporting 7 pieces when the planning quantity is 10 would be, “Did you scrap 3 pieces?”  Respond with “Y” and the system will report 7 pieces completed and 3 pieces scrapped.  Respond with “N” and the system will report 7 pieces completed and zero scrapped.
    • Whatever value is in the BOMP Global Setup, the operator can always press F5 for Detail Report to report the scrapped quantity.
  • If an error occurs when the operator enters a completed quantity, the system will ask you to use the F5 option.
  • Press F3 for Advance Options to inquiry the current production or your time clock entries.
  • If an exception occurs, the operator can press F4 for option to handle the exception.  The system will provide a list of options based on the authorization in the operator file.  If production has been reported for the operation, no option will be available.

 

If an operator reports complete quantity for the production, the system will prompt for addition information depending on the operation type.

  • Material Issued Reporting Screen, if this operation is a material issued point.
  • Serial Number Reporting Screen, if the parent item is a serialized item and the operation is the last operation.
  • Lot Number Screen, if the parent item is a lot item and the operation is the last operation. The system will ask the operator to report this in the detail reporting screen.
  • PO Information Screen, if the operation is an outside process operation.

Details about these screens can be found in the Report Additional Information section.

 

You will be prompted “Are you sure?” after the quantity is entered.  This allows you to check your entry before continuing.  Also, check the literal to the right of End Date/Time.  This literal will reflect the reporting status and can be the following:

  • Production Reported – The operator successfully reported for the production.
  • Production Suspended – The operator did not report for the production and will be suspended.
  • Production Continued – The operator did not report for the production and will continue without an operator.
  • Production Canceled – The operator canceled the production.

If the order is going to be closed, the system will display “Order Complete” to the right of the quantity.  Press Enter to continue.

 

If a production is successfully reported, a production transaction will be created. If BOMP Global Setup field 21, Immediately Post For Completed Scan Trx, is “Y”, the operator will be able to post this transaction immediately.  Otherwise, a manager can review the production transactions before posting them.

 

After reporting the production, the prompt will return to the Operator ID field or Order Number field based on the BOMP Global Setup.

 

If the operator’s next activity is a break, meal break or End Of Day logoff, the system skips the third stage and automatically suspends or continues the production based on the setup in the work center file.

Bill of Material / Work Order Plus

  1. BM0000 Bill of Material Package Overview
  2. What Is Work Order Plus And Where Can I Find The Documentation
  3. Work Order Plus Questions and Answers
  4. How to Reverse Plus Work Order Production Entries
  5. Planning Lead Time by Calendar Days or Work Days?
  6. How to See Cost in BOMP Plus Work Order Production History Report
  7. How to Close Plus Work Order
  8. Why I Received "Nothing In Range" with Plus Work Order Printing
  9. Receive "Trx Not Complete" on BOMP Production Edit List/Journal
  10. Feature - Trap Bad Date/Timestamp on Time Clock
  11. Feature - Enhanced Production Routing File Bill of Material Screen
  12. Print Plus Work Order Menu Option Is Missing
  13. Feature - Item Last Received Date to Include BOMP Production Activity
  14. BM01S1 Bill of Material Audit Trail Report
  15. BM23S1 Bill of Material Set Component Activity Flags
  16. BM24S1 Bill of Material Resequence Component Items
  17. BM26S1A Bill of Material Copy COP Orders into BOMP
  18. BM27S1 Bill of Material Purge Complete Production Orders
  19. BM29S1 Bill of Material Post Engineering Changes
  20. BM30S1 Bill of Material Engineering Change History Report
  21. BM32S1 Bill of Material Job Distribution History Report
  22. BM33S1 Bill of Material Option Item Where-Used Report
  23. BM0100 Bill of Material Product Structure File Maintenance
  24. BM0200 Bill of Material Single Level Bill of Material Inquiry
  25. BM0300 Bill of Material Indented Bill of Material Inquiry
  26. BM0400 Bill of Material Single Level Where-Used Inquiry
  27. BM0500 Bill of Material Single Level Bill of Material
  28. BM0600 Bill of Material Indented Bill of Material Report
  29. BM0700 Bill of Material Single Level Where-Used Report
  30. Feature - BOMP Integrity Check Utility
  31. BM0800 Bill of Material End Item Where-Used Report
  32. BM0900 Bill of Material Summarized Bill of Material Report
  33. BM1000 Bill of Material Print Costed Bill of Material
  34. BM1100 Bill of Material Gross Requirements Report
  35. BM1200 Bill of Material Print Picking List by Bill
  36. BM1300 Bill of Material BOMP Setup
  37. BM1400S1 Bill of Material Reset Low Level Codes
  38. BM1501 Bill of Material Feature/Option Configuration Maintenance
  39. BM1601 Bill of Material Feature/Option Configuration Inquiry
  40. BM1700 Bill of Material Production Order Entry
  41. BM1800 Bill of Material Production Transaction Processing
  42. BM1900 Bill of Material Post Production Transactions
  43. BM2000 Bill of Material Print Production Work Orders
  44. BM2101 Bill of Material Job Code File Maintenance
  45. BM2201 Bill of Material Issue Serial/Lot Component Item
  46. BM2801 Bill of Material Engineering Change Processing
  47. BM3100 Bill of Material Production Transaction History Report
  48. BMDPTMNT Bill of Material Department Maintenance
  49. BMDISCN Bill of Material B/M Distribution Report
  50. BMDPTIME Bill of Material Department Time Clock
  51. BMINQMNU Bill of Material Work Order Inquiry
  52. BMITMVRS Bill of Material Production Cost Variance Report
  53. BMLABMNT Bill of Material Labor Grade
  54. BMOIDMNT Bill of Material Operation ID
  55. BMPRDANL Bill of Material Labor Performance Report
  56. BMRTGMNU Bill of Material Production Routing
  57. BMSCHSCN Bill of Material Production Schedule Report
  58. BMSPCMNT Bill of Material Special Operation
  59. BMWCMNT Bill of Material Work Center Maintenance
  60. BMWCTIME Bill of Material Work Center Time Clock
  61. BMWIPSCN Bill of Material WIP Report
  62. BMWOPROD Bill of Material Work Order Production
  63. BMWORSCN Bill of Material Production History Report for WO+
  64. Feature - Option to Control if Item Last Received Date Is Updated from BOMP
  65. I Can Not Delete Some BOMP Work Orders
  66. Feature - BOMP Work Order Entry - F3=Copy COP Ord Function Improvement
  67. Feature - BOMP Plus WO Inquiry Detail Screen to Display Avg Dir Labor Time in HH:MM:SS Format
  68. Feature - Gross Requirements Report Item/Qty CSV Import
  69. Feature - Gross Requirements Report COP Order Import
  70. Feature - Component Qty Calculation Options In F3 Copy Function in BOMP WO Entry
  71. Plus Work Order Transaction Can't Post
  72. Feature - Production Routing File Maintenance - Show Material Cost for Std, Avg, and Last Cost
  73. Some Users Do Not Have Right for F3=Detail or F5=Order Prod Option in Plus Work Order Inquiry
  74. Feature - Print Kit Parent on Work Order
  75. Feature - Transfer Batch on Material Work Order Inquiry Screen
  76. Feature - Print User Name and Transfer Batch Status on Work Order
  77. Feature - Show “Active” Operators in Operator File Inquiry
  78. Feature - Transfer Batch on Plus Work Order Inquiry Screen
  79. Feature - Ability to Start a Material Work Order
  80. Feature - Drill Down to Where Used from Stock Status Inquiry Screen
  81. Feature - Allow User to Choose Time Format on Plus Work Order Traveler (BM20P3T)
  82. Feature - Material Work Order Copy Product Structure
  83. Feature - Plus Work Order Copy Product Structure
  84. Freezing When Printing Costed Bill of Materials
  85. Feature - Create Material Shortage Tracking with Plus Work Order
  86. Close Work Order With Quantity That Is Not Fully Reported
  87. Feature - Disable Print Costed Bill of Material to Update Parent Cost
  88. Feature - Item Selection in Cost Master Maintenance
  89. Feature - Plus WO Operation Number Default Increment
  90. Feature - Print Totals on Material Production History Report
  91. Feature - Print Total Quantity Order/Completed on the Production Schedule Report
  92. Feature - Add Default for Material Pick List, "Print By Pick Sequence"
  93. Feature - Allow Password to be Required to Update Parent Cost in Inventory
  94. Feature - Production Time Not Captured Report
  95. Feature - Add "Related Quotes" Option to Where-Used Inquiry
  96. Feature - Allow Export to CSV File for End Item Where-Used Report

Feedback and Knowledge Base