Check if Work Order Operation Has Shortage Before Allowing to Close the Operation
A user reported a scenario that they have been picking parts real time and creating shortage reports. However, they discovered that some of the work orders were getting closed without OP10 being complete. The allocation goes away but inventory isn't reduced for any short parts. In a perfect world they would be caught up with their inventory transactions, and user should check any shortage components before complete last operation.
So it is suggested that Elliott should check if the work order operation has any shortage and stop the work order from close OP20 before OP10 parts are complete.
-
Avi Weissbard - Cybermac software LLC commented
I was going to add an idea to do that. I agree. User must complete the shortage or release it.