Feature - Replacement Sales Order Import to Keep Changed Promise Date
Release Date: 10/17/2017
A new feature has been added to the CP/Util-setup/Sales Order Import/Import/Replacement Sales Order Import process that will keep a changed Promise Date when the import is done and the order already exists.
To enable this feature, go to Util-Setup/Global Setup/Add-Ons/Sales Order Import. Enter "Y" in field "25. Replace Order to Retain Original Promise Date?"
When the import runs, the report will now show the promise date. If the date was previously changed in Order Entry, the changed date will show in the Prom-Dt column. If the value was not changed, both Req-Date and Prom-Dt will be the same value.
Modified program: CPORDIMP.CBL